Crossroads tunnel under prison wall”
Case Study
Townsville
Correctional Centre
Stuart, Townsville – North Queensland
Authorities today have released the names of a professional organisation responsible for tunnelling
under the inner and outer walls of the Townsville Correctional Centre at Stuart in North Queensland.
“Tunnelling is what we do, we can tunnel under almost anything, for any reason, “Crossroads
Horizontal Boring Managing Director Ian Murdoch said, “as long as its legal” he added with a smirk.
The job at the Townsville Prison was undertaken by Crossroads Horizontal Boring through primary
contractor Baulderstone Hornibrook. The purpose of this project was to install the vital
infrastructure that the new facilities will require. This infrastructure included line and grade work
for the installation of facilities including sewerage, water, irrigation, and diesel lines. Other services
that were connected include those required for communications, gas and power.
The $142 million expansion will see an additional 200 cells added to the Townsville Correctional
Centre. The job commenced with the demolition of the 96 existing cells and is one of the largest jail
refurbishment projects that have been undertaken in North Queensland.
The total number of bores for this job exceeded 14 and a total of 725 metres of pipe ranging
between 300mm and 900mm were installed in the prison grounds. The project used a combination
of pipe jacking and directional drilling as traditional excavation techniques were not suitable due to
the potential security risks they posed.
“This job provided us with a lot of challenges,” Mr Murdoch said. “Firstly all of my staff had to
undergo security clearances before they were allowed to enter the site. All of our equipment had to
be scrutinised before entering and leaving the compound and all drilling procedures had to be
checked and double checked by the principle contractor before we could commence work.”
“At the end of each day, our worksite had to be completely secured and inspected,” Mr Murdoch
said. “Nothing could be left to chance. We even had an armed escort whilst working on site.”
For further information on this job and other services that have been performed by the team at
Crossroads Horizontal Boring or if you just require a quick tunnel to get you out of trouble, give us a
call on 07 4774 6333.
Case Study
Job: Townsville Correctional Centre
Stuart, Townsville – North Queensland
Authorities today have released the names of a professional organisation responsible for tunnelling under the inner and outer walls of the Townsville Correctional Centre at Stuart in North Queensland.
“Tunnelling is what we do, we can tunnel under almost anything, for any reason,“ Crossroads Horizontal Boring Managing Director Ian Murdoch said, “as long as its legal” he added with a smirk.
The job at the Townsville Prison was undertaken by Crossroads Horizontal Boring through primary contractor Baulderstone Hornibrook. The purpose of this project was to install the vital infrastructure that the new facilities will require. This infrastructure included line and grade work for the installation of facilities including sewerage, water, irrigation, and diesel lines.
Other services that were connected include those required for communications, gas and power.
The $142 million expansion will see an additional 200 cells added to the Townsville Correctional Centre. The job commenced with the demolition of the 96 existing cells and is one of the largest jail refurbishment projects that have been undertaken in North Queensland.
The total number of bores for this job exceeded 14 and a total of 725 metres of pipe ranging between 300mm and 900mm were installed in the prison grounds. The project used a combination of pipe jacking and directional drilling as traditional excavation techniques were not suitable due to the potential security risks they posed.
“This job provided us with a lot of challenges,” Mr Murdoch said. “Firstly all of my staff had to undergo security clearances before they were allowed to enter the site. All of our equipment had to be scrutinised before entering and leaving the compound and all drilling procedures had to be checked and double checked by the principle contractor before we could commence work.”
“At the end of each day, our worksite had to be completely secured and inspected,” Mr Murdoch said. “Nothing could be left to chance. We even had an armed escort whilst working on site.”
For further information on this job and other services that have been performed by the team at Crossroads Horizontal Boring or if you just require a quick tunnel to get you out of trouble, give us a call on 07 4774 6333.